THAT Council approve the following four (4) recommended energy retrofit projects for Royal LePage Place:
- ECM-2: Controls Optimization;
- ECM-4: Optimization of Dehumidifier Operation;
- ECM-5A: 100 Ton Heat Pump; and
- ECM-7: Desuperheater
as identified in the report titled “Energy Retrofits Update – Royal LePage Place” from the Facilities and Recreation Manager, dated April 22, 2025;
AND THAT the Mayor and Corporate Officer be authorized to execute the updated Fortis BC Implementation Letter dated March 13, 2025 to receive approximately $540,428 for completing the four (4) energy retrofit projects;
AND FURTHER THAT Council approve a budget amendment of an additional $246,500, to increase the budget from $1,153,260 to $1,400,000, for the four (4) energy retrofit projects at a net cost of approximately $859,572 to be funded through the finance strategy identified in this report.